BE INSPIRED WITH UNIQUENESS

BE INSPIRED WITH LIFE

Be unique and get Inspired with luxury living in Trivandrum. In a world of diversity, let your unique style shine through. At Arcon, we offer a lifestyle that is as unique as you are. Our luxury apartments in Trivandrum are designed to not only express your personality but also provide a comfortable and inspiring living space. Experience a home of modern living in one of the best apartments in Trivandrum. With our luxurious amenities and prime locations, Arcon Inspire offers a truly exceptional lifestyle. Feel the uniqueness in your lifestyle aspirations.

BE INSPIRED WITH LUXURY

Strategically located in the most happening place of Thiruvananthapuram, Inspire overlooks the city’s skyline as well as the sprawling acres of coconut groves. It offers you a total of 74 stylish apartments laid out in G+19 floors that enable you to make the most of life. Get amazed with the impressive amenities and best of facilities, especially the 3 floor car parking, which is one of its kind. With a contemporary site plan and an impressive range of square feet, we offer 1, 2 & 3 BHK apartments that boast of the highest of standards of building materials.

BE INSPIRED WITH LOCATION

Renowned for its picturesque beauty, Thiruvananthapuram is mostly celebrated for its rich cultural heritage. Few cities in the world can match this iconic city. Blending fine aspects of a perfect living, Inspire is extremely upscale as it is located at one of the well-established neighbourhood near Technopark, the renowned IT hub in the city. Multi-national companies, educational institutions and hospitals along with tourist destinations like Akkulam, malls like Lulu (upcoming project) are located in the close proximity of this premium residential arena.

BE INSPIRED WITH LIFESTYLE

Just like YOU, Inspire has its own unique character and a strong aspect of recreation. With modern amenities that let you enjoy life to the fullest, we bring you host of features that make your lifestyle the envy of others.
Designer entrance lobby with visitors lounge| Children’s play area with equipments| Visitors car parking| Association Hall/Multi-purpose Hall| Air-conditioned movie lounge| Fully equipped, Air-conditioned unisex gym| Infinity pool with changing room & Toilet| Roof top party area| Solar panel for common area lighting| Intercom facility between apartments & Security cabin| Biometric access card entry| Power back-up for each apartment| Reticulated Gas supply| DTH/Cable provision for living & master bedroom| Sewage water treatment plant| Individual letter box| CCTV surveillance camera in key areas| Provision for Wi-fi internet| Gas leakage detector| Common toilet for service staff

Structure
  • RCC framed structure complying with seismic zone 3 designs and as per the structural design. Concrete grade and steel grade be as per structural consultant’s advice.
Doors & Windows
  • Entrance door – Teak Veneered Paneled Door with flush shutters.
  • Internal doors – Hardwood Frames and flush door shutter.
  • Window Shutters : Engineered door frame with water resistant moulded shutter.
  • Hardware – All hardware will be in C.P/Brass.
  • Locks : Main Door &Bed Room door Locks will be mortise of Godrej/Dorset/Ozone/Sifon make and Toilet Doors will have “dead” latch of Hafele /Ozone/Sifon
  • All regular windows, ventilators and balcony sliding doors will be powder coated aluminium with 5mm glass
Electrical
  • Concealed copper wiring shall be done for lighting, fans, power points, AC points using RR cable/Havells Standard/Havells /Poly cab
  • Wired provision for the water heater point and exhaust fan point shall be provided for all the apartment toilets
  • Wired provision for telephone and internet point shall be provided in the living room & master bed room.
  • Wired provision for cable TV/DTH in the living room & master bed room.
  • Switches: Modular plate switches shall be provided Legrand (Lincus)/Schneider(Livia)/Havells(Fabio)
  • Adequate ELCB and MCB shall be provided in each apartment using Legrand/Schneider/Havells.
  • DG Power Back up : Power back up will be provided for all common service and selected light and fan points in living, bed rooms ,TV points and a refrigerator point shall be provided .power back up to maximum 600W for each apartment. (AC point, water heater point and other16Ams point will not be considered for the power back up).
  • Light Fixtures: For Common areas, Garden areas and at the top of Main entrance door of individual apartments.
Sanitary & Plumbing
  •  Master Bed Room Toilet : Wall-hung EWC with concealed flush tanks. Vanity Counter and Wash bowls. All sanitary fittings shall be of CERA, ESSCO by Jaguar.
  •  Other Bedroom Toilet : Wall hung EWC with concealed flush tanks, wall hung wash basin. All sanitary fittings shall be of CERA/ESSCO by Jaquar.
  •  Concealed Cistern : (Concealed flushing system)– will be of GEBRIT/CERA/JAQUAR.
  •  CP fittings of all toilets : Single lever concealed diverter for shower and spout. Pillar tap shall be provided for washbasin, health faucet with angle valve shall be provided in all bathrooms. All fittings shall be of CERA/ESSCO by Jaquar.
  •  Hot Water : Provision for hot water will be provided for all apartment’s overhead shower and spout only.
  •  Pipes : All supply lines will be with ISI marked CPVC/PVC pipes.
  •  Kitchen & Work Area : Wall mounted Faucets taps using ESSCO by JAGUAR/CERA brand.
  •  Kitchen Sink : Stainless Steel sink single bowl with drain board of ISI make for Kitchen, and stainless sink without drain board will be provided for the work area shall be of Prince/Metro.
  •  Accessories : Accessories like Towel rods, Soap Dish with C.P. finish will be provided inside the toilets. Towel ring shall be provided near dining washbasin.
Flooring & Tiling + Railing
  • Lift lobby and fascia using composite marble/granite/vitrified tile as per the architects design.
  • Staircase using vitrified tile and hand railing using MS / G.I sections as per architects design.
  • Car park Area: For Ground floor seamless VDF flooring with groove/ exterior grade paving tile as per the architects design in specific areas. For First and second floor finished with cement mortar screeding with groove.
  • Foyer/Living/Dining/Bed Rooms/Kitchen using 80cm x 80cm vitrified tiles of CERA/KAJARIA/AGL/JOHNSON/QTONE as per architects design.
  • Toilets: Ceramic tile for floor and for walls up to door height as per architects design.
  • Balconies: Rustic or antiskid ceramic tiles and G.I railings as per architects design up to 1.20M minimum height.
Painting
  • Regular wall Emulsion paint with putty finish using Asian/Berger/Nerolac in all apartments and in the common areas and utility services areas.
  • Regular ceiling emulsion paint Asian/ Berger/Nerolac for the ceiling inside apartments & common areas.
  • External Walls: Weather proof/exterior grade emulsion using Asian/Berger/Nerolac.
Elevators
  • Elevators – 3 Nos. will be provided with automatic doors of OTIS/JHONSON/THYSSENKRUP/FUJITEC/ESCON
Air Conditioning
  • Wired provision for installing split Air-conditioners will be provided for all bed rooms.
Automation
  • Access control entry at main entrance lobby area.
  • Gas leakage cut out valves will be provided in each apartment
Landscaping
  • Interlock Pavers to be laid in driveways.
  • Entrance Gate.
Water & Electricity
  • Bore well water shall be provided through UG sump and overhead tank for drinking and non-drinking purposes.
  • Kerala Water Authority water connection can be made available at extra cost. The extra cost will include labour charges, material charges, deposits, tar cutting charges and all other relevant charges to take the connection from Kerala water Authority connection point to UG sump.
  • 3 Phase electricity shall be provided.

Amenities & Features

  • Air conditioned designer entrance lobby with visitors lounge.

  • Roof top swimming pool with changing room and toilet.

  • AC mini movie lounge.

  • Air conditioned unisex gym with 2Nos motorized tread mill, 1No elliptical cross trainer, 1No home gym.

  • Children’s play area with equipment.

  • Association room.

  • Multipurpose hall.

  • Solar panel for lightning in lobby areas.

  • Roof top party area.

  • Intercom facility between apartment & security cabin.

  • Biometric access card entry at main entrance.

  • Generator back - up for common areas and designated points in the apartment with maximum back up of 600W.

  • Provision for reticulated gas supply.

  • Wired provision for DTH/Cable provision for living and master bedroom.

  • CCTV surveillance cameras in key area.

  • Sewage treatment plant or drainage connection (if available at extra cost).

  • Individual letter box.

  • Wired provision for Wi-Fi internet.

  • Gas leakage detector in gas bank room.

  • Common toilet for service staff.

  • Care taker room.

  • Changing room for servants.

Sample Apartment

05-1-2023

Block Work – 100% completed

Ceiling Plastering – 100% completed

Internal Wall Plastering – 100% completed

External Wall Plastering – 100%

Electrical Work (Wall Chasing & Box Fixing)
15th Floor 100%
16th Floor 100%
17th Floor 100%
18th Floor 100%
19th Floor 100%
20th Floor 100%

Electrical Work (Wire Pulling)
1st to 20th Floor 100%

Waterproofing
Ground Floor 100%
3rd Floor to 20th Floor 100%
OHT 100%

Plumbing ( Toilet Pipe Line Work ) – 100% completed

Painting ( Inside Putty Work )
Ground Floor to 2nd Floor 95%
3rd Floor to 19th Floor 98%
Outside 1 Coat Putty 100%

Tiling Work
Ground Floor to 2nd Floor to 19th Floor 99%

Fabrication work – 96%

Fire Fighting Work – 90%

HT Work – 100%

False Ceiling 3rd to 17th

Floor – 100%

Service Lift – 100%,

Passenger Lift – 95%

GF Yard, Compound Wall – 75%

Swimming Pool Work – 100%

STP – 95%

WTP – 100%

Aluminium Work – 95%

27-09-2022

Block work
18th floor 100%
19th floor 100%
20th floor 100%

Ceiling Plastering
19th floor 100%
20th floor 100%

Internal Wall Plastering
19th floor 100%
20th floor 100%

External Wall Plastering – 98%
Electrical Work (Wall Chasing & Box Fixing)
18th floor 100%
19th floor 100%
20th floor 100%

Electrical Work (Wire Pulling)
3rd – 20th floor 90%

Waterproofing
Ground Fl0or 50%
3rd – 20th floor 100%
OHT 100%

Plumbing (Toilet pipe line work)
17th floor 100%
18th floor 100%
19th floor 100%

Painting (Inside putty work)
12th floor 90%
13th floor 90%
14th floor 90%
15th floor 90%
16th floor 90%
17th floor 90%
18th floor 90%
19th floor 90%
outside 1 coat putty – 90%

Tiling work 
3rd – 19th floor 95%

Fabrication work – 75%

Fire fighting Work – 70%

HT Work – 65%

False ceiling 3-17th floor – 60%

Service lift – 40%
GF Yard, compound wall – 30%

01-08-2022

Block work
16th floor 100%
17th floor 100%
18th floor 100%
19th floor 100%
20th floor 100%

Ceiling Plastering
17th floor 100%
18th floor 100%
19th floor 100%
20th floor 100%

Internal Wall Plastering
15th floor 100%
16th floor 100%
17th floor 100%
18th floor 100%
19th floor 100%
20th floor 100%

External Wall Plastering – 90%
Electrical Work(Wall Chasing & Box Fixing)
15th floor 100%
16th floor 100%
17th floor 100%
18th floor 100%
19th floor 100%
20th floor 100%

Electrical Work (Wire Pulling)
3rd – 17th floor 85%

Waterproofing
3rd – 17th floor 95%

Plumbing (Toilet pipe line work)
15th floor 100%
16th floor 100%
17th floor 100%
18th floor 50%
19th floor 50%

Painting (Inside putty work)
12th floor 80%
13th floor 80%
14th floor 80%
15th floor 80%
16th floor 80%
17th floor 80%
18th floor 80%
outside 1coat putty – 55%

Tilingwork
3rd – 13th floor 80%

Fabrication work – 65%

Fire fighting Work – 50%

HT Work – 45%

 

03-05-2022

Block work
16th floor 100%
17th floor – 100%
18th floor 100%
19th floor – 100%
20h floor – 5%

Ceiling Plastering
17th floor – 100%
18th floor – 30%

Internal wall plastering
15th floor – 100%
16th floor – 100%
17th floor – 100%
18th floor – 100%

External wall plastering – 60%

Electrical Work(Wall chasing & Box fixing)
17th floor – 100%
18th floor – 100%

Waterproofing
9th floor – 70%
10th floor – 70%
11th floor – 70%
12th floor – 70%
13th floor – 70%
14th floor – 70%
15th floor – 70%
16th floor – 70%
16th floor – 20%

Plumbing (Toilet pipe line work)
15th floor – 100%
16th floor – 100%
17th floor – 100%

Painting (Inside putty work)
12th floor – 80%
13th floor – 80%
14th floor – 80%
15th floor – 80%
16th floor – 80%
17th floor – 80%

Tilingwork
3rd floor – 40%
4th floor – 40%
5th floor – 40%
6th floor – 5%
Fabrication work – 50%
Fire fighting Work – 25%

05-01-2022

Block work
11th to 14th floor – 100%
15th floor – 30%

Ceiling Plastering
11th to 15th floor – 100%
16th floor – 30%

Internal wall plastering
6th to 12th floor – 100%
13th floor – 70%
14th floor – 50%

Electrical Work(Wall chasing & Box fixing)
9th to 14th floor – 100%

Waterproofing
3rd to 8th floor – 60%

Plumbing (Toilet pipe line work)
3rd to 8th floor – 100%
9th floor – 50%

Painting (Inside putty+Primer work)
3rd to 9th floor – 80%

19-11-2021

Floor slab upto 17th floor – 100%

Block work upto 12th floor – 100%

Block work upto 13th floor – 40%

Internal Wall plastering up to 10th floor – 100%

Internal Wall plastering up to 11th floor – 75%

Internal Wall plastering up to 12th floor – 35%

Electrical work (Wall chasing & Box fixing) upto Floor – 100%

Water proofing in 3rd floor – 100%

Water proofing in 6th floor – 60%

Putty & Primer work upto 3rd floor – 100%

Putty & Primer work upto 6th floor – 80%

Plumbing work up to 6th floor – 100%

Ceiling Plastering 14th floor – 100%

15-09-2021

Floor slab upto 15th floor – 100%

Block work upto 10th floor – 100%

Internal Wall plastering up to 8th floor – 100%

Electrical work (Box fixing upto 9th floor – 100%

Water proofing in 3rd floor – 60%

Putty & Primer work upto 4th floor – 60%

Plumbing work up to 3rd floor – 80%

10-07-2021

13th floor slab work – 100%

Block Work 8th Floors – 100%

Block Work 9th Floor – 75%

Block Work 10th Floor – 10%

Ceiling Plastering 10th Floor – 100%

Internal wall plastering – 5th floor – 50%

Electrical Work – Box

Fixing upto 6th floor – 100%

Waterproofing – 3rd floor – 10%

11-05-2021

12th floor slab – 50%

Block Work 4,5,7th Floors – 100%

Block Work 8th Floor – 10%

Ceiling Plastering 1st,9th Floor – 100%

Electrical Wall Chasing 3rd, 4th Floor – 100%

Electrical Wall Chasing 5th Floor – 90%

20-10-2020

7th floor slab completed – 100%

04-10-2019

Grade Beam Casting

Completed

Column Casting ( Ground Floor ) Completed

Shear Wall Casting Completed

Ground Floor Roof Slab

Shuttering Work 60%

Ground Floor Roof Slab Steel Work 56 %

Ground Floor Roof Slab Concreting Work 56 %

03-05-2019

Piling Work Completed

Life well Casting Completed

Pile Cap Casting 40% ( 35 no’s pile caps has been completed )

Grade Beam Casting 20%

Column Casting 6 %

Pile Cap Chipping 50 %

Arcon Inspire - Bhoomi Pooja Ceremony

Project Status